Project

EO REACTOR

Project

Lifting of 1 Critical Items @ Pars Phenol Petrochemical Project.

Location

Iran

Load Detail

Critical equipment was – Dia 6.7m x 24m long – 888 te

Scope of work

Complete Engineering Service

Detail of Work

Creative has provided detailed Engineering Solution to our client for lifting of EO Reactor In Pars Phenol Petrochemical Project @ Iran. Project execution has been carried out by using has Demag CC6800 and CC2200 cranes. Crane utilization for main crane was 92%.